Tasks

Save is unavailable on a new task

!

Issue

On a new task, you can't click Save, and it shows Add an assignee.

Cause

The task is a P2P task, and a P2P task needs at least one assignee.

Solution

  1. Under Assignees, add a person. To assign the task to yourself, click your name under Watchers > Move to Assignees.
  2. Click Save.

You can't complete or discard a task

!

Issue

You can open a task in your team's project, but you can't complete or discard it.

Cause

Only the people on a task can change its status: its creator, assignees, and watchers.

Solution

  1. On the task, click Watch. You're now on the task.
  2. Click Complete, or click ⋯ > Discard.

A completed task can't be edited

i

Info

You can't change the title, people, or fields of a completed or discarded task.

Cause

Tasket locks completed and discarded tasks, so their record doesn't change.

Solution

  1. On the task, click Re-open.
  2. Optional: add a note to say why, and confirm. You can now edit the task.

A project isn't offered when you move a task

!

Issue

The project you want isn't in the list when you click Change Project.

Cause

The project belongs to another team. Tasks can move only between projects of the same team.

Solution

  1. In the other team's project, create a new task.
  2. In the new task's Linked Tasks, click Select under Linked, and select the original task.

Projects

The Intakes tab asks for a team admin

i

Info

The project's Intakes tab shows Ask a team admin to enable Intakes.

Cause

Intakes are turned off for the project, and only team admins can turn them on.

Solution

  1. Ask a team admin to open the project's Settings > Features.
  2. They turn on Enable Intakes. The Intakes tab is ready to use.

A sprint name is already used

×

Error

Tasket shows Duplicate sprint name when you create or rename a sprint.

Cause

Another sprint in the project has the same name, even if it's closed. Capital letters don't make a name different.

Solution

  1. Enter a different name, for example add the month: Sprint 4 November.
  2. Press Enter.

Teams

The last team admin can't be removed

×

Error

Tasket shows Cannot remove last admin or Cannot demote last admin.

Cause

A team always needs at least one admin.

Solution

  1. In the team, click Settings > Members.
  2. Change another member's role to Admin.
  3. Remove or change the role of the first admin.

A guest's email address isn't accepted

×

Error

You can't add a guest with their email address.

Cause

The address is a personal address, such as Gmail, or it belongs to your own organisation. Guests must use a work email address from another organisation.

Solution

  1. Ask the guest for their work email address, and add that instead.
  2. If the person is in your organisation, add them as a member. See Invite members and guests.

Need help?